Nagpur: Nearly 900 development works in the city have administrative approval. What they do not have is a tender.
With four months left in the financial year, the Nagpur Municipal Corporation's accounts and finance department issued a circular on Monday asking all departmental heads to prepare revised budget estimates for 2026-27 and proposals for the 2027-28 budget. The exercise is being read inside the civic body as a scramble. Files that have cleared the first gate are stuck before the tendering stage, and without work orders by March 31, both the works and their financial liabilities will roll into the next year.
Two things slowed the queue. Two model code of conduct periods for legislative council elections took nearly three months out of the working year. And the corporation's new work module, introduced to track development proposals more closely, slowed the movement of files while staff get used to it.
The backlog has reached the elected wing. Ruling party leader Narendra Borkar, along with around 60 BJP corporators, met municipal commissioner Vipin Itankar to flag the pendency of proposals under the new system. Leader of opposition Sanjay Mahakalkar said he would raise the matter at the coming general body meeting and seek an explanation from the administration.
Money is the other half of the problem. The standing committee, under chairperson Shivani Dani-Wakhare, has set a budget target of Rs 6,200 crore. Revised estimates will force every department to rework what it can actually spend this year against what it promised.
For a corporator, the arithmetic is simple. An approved work that misses the tender stage in a financial year does not begin before the next one.
The general body meeting is expected to take the question up. The financial year ends on March 31.