Patna: Bihar has signed up for a hyperscale data centre, a category of infrastructure the state has never hosted.
CtrlS Datacenters signed a memorandum of understanding with the state government on November 20 for a Rs 10,000 crore, 150 MW AI-ready facility. Commercial operations are targeted for 2029-30.
The company had issued a letter of intent in October. The MoU converts that into a commitment, and the site preference has shifted to land near Patna.
About 400 direct jobs are expected from the project, according to the company's own estimate.
The plant is being billed as AI-ready, which in data centre language means high power density per rack, liquid cooling provision and the kind of connectivity that training and inference workloads need. Whether Bihar's grid can carry 150 MW to a single campus, and at what tariff, is the question the project will have to answer.
Bihar is not the only state chasing this business. Maharashtra is simultaneously working on a water supply arrangement for data centres through a MIDC subsidiary, and has set up a 17-member committee under former Atomic Energy Commission chairman Anil Kakodkar to study the environmental and infrastructure load of such facilities.
Water and power are the two constraints that decide where data centres land. A 150 MW campus draws roughly what a mid-sized city does, and cooling it takes water that has to come from somewhere.
CtrlS is a homegrown operator with campuses in multiple Indian cities. Its Bihar commitment is one of the largest single private infrastructure investments announced in the state in recent years.
The state government has been positioning Bihar as a back-office and services destination. A data centre is a different bet, and a longer one — the returns run over a decade, not a quarter.